A hardship clause is a contract provision that addresses situations where unforeseen events fundamentally alter the equilibrium of a contract, making performance excessively burdensome for one party without rendering it impossible. It typically obligates the parties to renegotiate the terms and, if negotiation fails, provides for contract adaptation or termination by a third party or by one of the parties. Unlike force majeure, hardship aims to keep the contract alive on adjusted terms rather than providing an exit.
When performance remains possible but turns economically ruinous due to events like sudden tariffs, currency devaluation, or supply chain shocks, neither force majeure nor legal doctrines of impossibility provide a solution. Force majeure excuses performance; hardship adapts the contract. A well-drafted hardship clause provides the agreed procedure for such situations: the parties sit down to renegotiate and restore the balance, with a predefined fallback if they cannot agree.
Despite its importance, most commercial contracts lack a dedicated hardship clause, leaving parties to rely on uncertain statutory interpretations (e.g., Section 313 BGB in Germany) or the contested application of Article 79 CISG, which offers no duty to renegotiate or judicial adaptation.
The distinction is not word-splitting; it decides the legal consequence. The difference lies in the effect on performance, not the triggering event.
| Aspect | Hardship Clause | Force Majeure Clause |
|---|---|---|
| Effect on Performance | Performance remains possible but has become excessively burdensome or economically unreasonable. | Performance becomes impossible or temporarily prevented. |
| Legal Consequence | Renegotiation and adaptation of the contract terms to restore balance. | Suspension or termination of the contract; the party is excused from performance. |
| Objective | To keep the contract alive on new, fair terms. | To provide an emergency exit from the contract. |
| Typical Trigger | Drastic economic changes, new regulations, tariff increases, currency devaluation. | Natural disasters, wars, export bans, pandemics (when making performance impossible). |
While an export ban that makes delivery absolutely impossible is force majeure, a tariff increase that merely makes the same delivery more expensive is a case for hardship and price adjustment. Both belong in the same contract, but in two separate clauses, as reflected in the ICC model clauses.
Whether a hardship clause is needed depends heavily on the applicable law. The answers differ markedly across legal systems.
| Legal System | Statutory Adjustment for Hardship? | Consequence for the Clause |
|---|---|---|
| Germany (Section 313 BGB) | Yes, adjustment is possible (‘Störung der Geschäftsgrundlage’), but no statutory duty to renegotiate, applied with restraint. | The clause sharpens the threshold, defines procedure, and creates a duty to renegotiate. |
| France (Article 1195 Civil Code) | Yes, since 2016 (imprévision): renegotiation, then judicial adaptation or termination. | The clause can modify or exclude the statutory model. |
| Italy (Article 1467 Civil Code) | Yes, for eccessiva onerosità: termination in principle, adaptation only on the other side’s offer. | The clause supplies the missing adaptation mechanism by the affected party. |
| Common Law (England, USA) | No: no judicial adaptation; frustration only within narrow limits. | The clause is indispensable; it creates what the law refuses. |
| CISG (Article 79) | Contested. Even if applicable, no duty to renegotiate or judicial adaptation. | A clause is essential to create renegotiation and adaptation mechanisms. |
In common law jurisdictions, judicial adaptation of the contract is unknown. A bare duty to negotiate is often unenforceable as an ‘agreement to agree’. Therefore, English hardship clauses typically delegate the decision to a third party (arbitral tribunal or expert), making the choice of ICC Option 3B more than a nicety,it creates the power to adapt that the law itself refuses.
The International Chamber of Commerce (ICC) provides two coordinated model clauses,one for force majeure and one for hardship. The hardship clause follows a clear logic and offers three options for what happens when renegotiation fails.
| ICC Hardship Clause Option | Consequence if Renegotiation Fails | Best Suited For |
|---|---|---|
| Option 3A | The affected party may terminate the contract; adaptation by a judge or arbitrator is excluded without the other side’s consent. | Parties that do not want judicial adaptation and, in case of doubt, prefer a clean exit. |
| Option 3B | Either party may ask the judge or arbitrator, who adapts the contract to restore its equilibrium or terminates it, whichever is appropriate. | Parties that want to hold on to the contract, with the option of adapting it. This is the preferred option for contracts meant to be adapted. |
| Option 3C | Either party may ask the judge or arbitrator to declare the contract terminated. | Parties that want to leave termination, but not adaptation, to the court or tribunal. |
The clause is deliberately pitched above mere difficulty. It requires that performance has become excessively onerous, not merely more expensive, and that the event was neither foreseeable nor avoidable at the time of contracting. The choice of option allocates power: Option 3B gives the judge or arbitrator the strongest power,adaptation of the contract against the will of one side, which is precisely what the CISG does not provide.
A party drafting a hardship clause should decide five questions, in this order:
When is performance “excessively burdensome”? Use objective indicators (e.g., cost increase of X%, material change in exchange rate) rather than vague terms like “economic difficulty.”
Establish a clear negotiation process: notice requirements, timeframes, and who represents each party in the renegotiation.
Decide who decides if negotiations fail: one of the parties, an arbitral tribunal, or an expert. Option 3B is the most robust for preserving the contract.
If the clause is imposed unilaterally (not negotiated), it may be subject to content review under national laws (e.g., German AGB review). The ICC clause is publicly available, which supports transparency, but incorporation by reference may still be risky. Writing the full text into the contract is more transparent.
Ensure the hardship clause is consistent with the force majeure clause, price adjustment mechanisms, and dispute resolution provisions. Do not merge the two types of clauses.
If a hardship clause is imposed as standard terms (not individually negotiated), it must be transparent and not unreasonably disadvantage the other party. While relevant clauses are generally recognized and take precedence over Section 313 BGB, a clause that blurs the trigger and consequences risks invalidity due to lack of transparency. The ICC clause is well-drafted and publicly available, which reduces this risk, but incorporation by reference alone may be insufficient in some jurisdictions.
Hardship clauses are increasingly relevant in volatile global markets. Common triggers include:
The key is that the event must be beyond the party’s control, not foreseeable at the time of contracting, and it must make performance excessively onerous,not merely more difficult or slightly more expensive.
Mistake: Treating a cost increase as a force majeure event. Reality: If performance is still possible, force majeure does not apply. The correct tool is a hardship clause, which leads to renegotiation, not excuse.
Mistake: Relying on Section 313 BGB or Article 79 CISG to solve a hardship situation. Reality: Section 313 BGB offers no duty to renegotiate, and Article 79 CISG (even if applicable) offers no judicial adaptation. A dedicated clause is essential.
Mistake: Using ambiguous terms like “economic difficulty” or “substantial change.” Reality: Such clauses are difficult to enforce. The trigger must be objective (e.g., cost increase of X%, currency devaluation of Y%).
Mistake: Combining both into one clause. Reality: Merging them mixes two different sets of conditions with two different consequences, leading to confusion and potential invalidity. They should be drafted as two separate, coordinated clauses.
Mistake: Incorporating the ICC clause by reference without negotiation. Reality: The clause may be subject to content review if imposed. Writing the full text into the contract and negotiating the key terms (especially the choice of Option 3A, 3B, or 3C) is safer.

They represents the product, and research team behind GTsetu, a global B2B collaboration platform built to help companies explore cross-border partnerships with clarity and trust. The team focuses on simplifying early-stage international business discovery by combining structured company profiles, verification-led access, and controlled collaboration workflows.
With a strong emphasis on trust, and disciplined engagement, Team GTsetu shares insights on global trade, partnerships, and cross-border collaboration, helping businesses make informed decisions before entering deeper commercial discussions.